State Route 4 Angels Camp Bypass

Description: In Angels Camp, from the north junction of Route 49 to east of Rolleri Road. Construct 2-lane expressway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Calaveras
City Angels City
Zip Code 95222
 
Senate District
01
Assembly District 25
Congressional District 03
 
Caltrans District
10
 
 
County/State Route Calaveras 4
Postmile Begin/End R  21.1 R  23.4
 
County/State Route Calaveras 4
Postmile Begin/End R  21.2 R  23.4
 
County/State Route Calaveras 4
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  184      
Lane Miles Added (Mixed)  4.6    4.6  
Peak Period Time Savings (minutes)  7320      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Design (PS&E) Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Right of Way Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Construction Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
 
Corridor System Management Plan
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
IIP Augmentation
$0 $0 $0
CMIA
$4,438 $-864 $3,574
Non-bond Funding
State/Federal*
$57,114 $0 $57,114
Non Budgeted ETC
$0 $0 $0
 
Total**** $61,552 $-864 $60,688

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,678 $0 $1,678 $1,686
Design(PS&E)
$3,374 $0 $3,374 $4,326
Right of Way
$20,935 $0 $20,935 $22,677
Construction
$35,565 $-864 $34,701 $30,292
 
Total* $61,552 $-864 $60,688 $58,981

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
08/01/1998 

06/01/2002 
 

 
08/01/1998 

06/01/2002 
100  08/12/1998 

06/28/2002 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2002 

06/01/2006 
 

 
06/01/2002 

06/01/2006 
100  06/01/2002 

06/22/2006 


-1 
Begin Right of Way Phase

End Right of Way Phase
06/01/2002 

05/01/2007 
 

 
06/01/2002 

05/01/2007 
100  06/01/2002 

06/16/2006 


11 
Begin Construction Phase

End Construction Phase
09/01/2007 

09/01/2010 
 

 
09/01/2007 

09/01/2010 
100  08/11/2007 

09/24/2009 


11 
Begin Closeout Phase

End Closeout Phase
02/01/2011 

03/01/2012 
 

 
02/01/2011 

03/01/2012 
100  10/01/2009 

06/15/2022 
16 

-125 
Corridor System Management Plan
Adoption Date 10/01/2008    10/01/2008   
Implementation Date 02/01/2009    02/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 184
Lane Miles Added (Mixed) 4.6 4.6
Peak Period Time Savings (minutes) 7320

Bond Funding Cost
Adopted:
$4,438,000
Current Approved:
$3,574,000
Actual Expenditures:
$3,574,000

 

Status as of December 31, 2023.