Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
State Route 4 Angels Camp Bypass |
Description: In Angels Camp, from the north junction of Route 49 to east of Rolleri Road. Construct 2-lane expressway.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Calaveras |
City | Angels City |
Zip Code | 95222 |
Senate District |
01 |
Assembly District | 25 |
Congressional District | 03 |
Caltrans District |
10 |
County/State Route | Calaveras 4 |
Postmile Begin/End | R 21.1 R 23.4 |
County/State Route | Calaveras 4 |
Postmile Begin/End | R 21.2 R 23.4 |
County/State Route | Calaveras 4 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 184 | |
Lane Miles Added (Mixed) | 4.6 | 4.6 |
Peak Period Time Savings (minutes) | 7320 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Right of Way Phase |
Caltrans | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Construction Phase |
Caltrans | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Melissa Ramos | (209) 941-1963 | melissa.ramos@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
IIP Augmentation |
$0 | $0 | $0 | ||||
CMIA |
$4,438 | $-864 | $3,574 | ||||
Non-bond Funding | |||||||
State/Federal* |
$57,114 | $0 | $57,114 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $61,552 | $-864 | $60,688 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,678 | $0 | $1,678 | $1,686 | |||
Design(PS&E) |
$3,374 | $0 | $3,374 | $4,326 | |||
Right of Way |
$20,935 | $0 | $20,935 | $22,677 | |||
Construction |
$35,565 | $-864 | $34,701 | $30,292 | |||
Total* | $61,552 | $-864 | $60,688 | $58,981 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
08/01/1998 06/01/2002 |
|
08/01/1998 06/01/2002 |
100 | 08/12/1998 06/28/2002 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/01/2002 06/01/2006 |
|
06/01/2002 06/01/2006 |
100 | 06/01/2002 06/22/2006 |
0 -1 |
|
Begin Right of Way Phase
End Right of Way Phase |
06/01/2002 05/01/2007 |
|
06/01/2002 05/01/2007 |
100 | 06/01/2002 06/16/2006 |
0 11 |
|
Begin Construction Phase
End Construction Phase |
09/01/2007 09/01/2010 |
|
09/01/2007 09/01/2010 |
100 | 08/11/2007 09/24/2009 |
1 11 |
|
Begin Closeout Phase
End Closeout Phase |
02/01/2011 03/01/2012 |
|
02/01/2011 03/01/2012 |
100 | 10/01/2009 06/15/2022 |
16 -125 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2008 | 10/01/2008 | 0 | 0 | |||
Implementation Date | 02/01/2009 | 02/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 184 | |
Lane Miles Added (Mixed) | 4.6 | 4.6 |
Peak Period Time Savings (minutes) | 7320 |
Bond Funding Cost | |
---|---|
Adopted: |
$4,438,000 |
Current Approved: |
$3,574,000 |
Actual Expenditures: |
$3,574,000 |
Status as of December 31, 2023.